Foundation Construction
After excavating our lot so that the pad was level the
concrete contractor came in and lined up the home and garage foundations. Forms were placed and then a small backhoe
came in and form trenches were dug along the outer portions of the foundation
(Exterior beam/footing), along areas where load bearing walls would be placed
and also along evenly spaced areas forming what looked liked a grid of support
beams Interior beams).
![]() |
Exterior Beam |
![]() |
Interior Beam |
After the trenching was done the construction crew literally
bagged limestone and caliche material to provide an inner support wall for the
foundation perimeter and support beam areas.
The bagging was done by laying out a sheet of black plastic,
filling an area along the edge with about 6" of fill then pulling the
plastic back, laying in more fill and then looping the plastic out and
repeating. The edges look like plastic
sand bags have been stacked up.
In areas where a stoop is planned actual sand bags are used.
Next comes the rough in plumbing which will be placed in and
around the fill and then the concrete crew will come back in and do the steel
reinforcing work.
No comments: